The Rescue Scenario

Shortly after the accident, during the third week in February 2003, a few of us contemplated if a rescue mission of Columbia’s crew could have been conducted. If it could, what were the chances of success?

Under the guidance of Shuttle Program managers we were asked to quietly study it. We were to conduct our studies in part to satisfy our own curiosity and in part knowing the Columbia Accident Investigation Board (CAIB) would no doubt ask us one day. The Flight Directors at Johnson Space Center (JSC) would do the on-orbit assessment, and I would do the Kennedy Space Center (KSC) operations assessment. The two would combine to answer the unfriendly—but necessary—question.

My part concluded that from a pure timing perspective, a rescue was theoretically possible. The result from JSC was the same: theoretically possible. But both required unrealistic assumptions and actions that were not consistent with the mission being flown, or usual program priorities or objectives.

Rescue would have involved having us launch Atlantis—next in line to fly—as soon as possible, rendezvous with Columbia, transfer the astronauts via some sort of tether to Atlantis, and come home. The crew of seven from Columbia would be aboard Atlantis with her rescue crew of four. Four of the crew members would have to ride home strapped to the deck; there were only seven seats on the orbiter. Columbia herself would then be guided to a ditching in the ocean.

At the time of the accident, Atlantis was almost ready to roll out of the Orbiter Processing Facility to the VAB. A full-court press to expedite that and get to the launch pad would be required. The Pad “flow” would be truncated to only those tasks required, the rest omitted to save time. Things like the Terminal Countdown Demonstration Test and cryogenic loading simulation would be eliminated. Other required tasks would be done three shifts per day, seven days per week. Meanwhile, the rescue scenario flight plan would be developed at JSC.

Assuming no significant glitches, launch could have been as early as February 11. This also assumed no significant processing or launch delays occurred, including weather. That also assumed that Atlantis would not have her remote manipulator arm installed, which was almost certainly needed for a rescue mission. Installing the arm would have pushed the earliest launch date to February 13.

If everything went according to plan—and that was a BIG if—the rescue would have happened two days before Columbia‘s consumables ran out. Columbia would have been in orbit for almost a full month by then, two weeks longer than any previous Shuttle mission.

The key to the entire study was that consumables on board Columbia needed to preserved as much as possible, extending Columbia’s time on orbit awaiting Atlantis’ arrival. Food, water, etc. all needed to be stretched to the max. The limiting commodity however were the lithium hydroxide (LiOH) canisters needed to scrub carbon dioxide from the cabin air. Not food, not water, not power, but the ability to provide breathable air for Columbia’s crew.

The assumption made for the study was that we needed to put the crew on alert for extending LiOH no later than Day 4 of the mission. The crew would have had to go into a very low activity mode to keep their respiration as low as possible. This would have had the effect of terminating the mission’s objectives, effectively ending the reason for the mission. To do this would have been one of the unrealistic moves required. AND, to even get to this posture would have required either proof that the Orbiter was fatally damaged by that day, or assuming so. That was another unrealistic assumption, since the request for additional imagery didn’t occur until Day 6 of the mission, by which time it would already have been too late to conserve the consumables.

But when the two studies were combined, we saw that it would have been technically possible to rescue the crew. That’s the cold, data-driven answer. The truth is that the assumptions I mentioned above, and a few others, would have required extraordinary efforts in both ground and mission operations AND management decision making while we were lacking definitive damage information. All this would have been far outside the normal Shuttle practices at the time.

It should also be noted that the decision to actually launch the rescue mission would have been an extraordinary thing in and of itself. Would we commit a crew of four on Atlantis to rescue Columbia’s, crew possibly facing the same damaging foam loss during its launch? A tough decision to say the least, bigger than NASA alone could make. I believe the President would have had a role in that decision.

But it never got to the point that we’d find out.

No rescue mission was ever contemplated during Columbia’s time on orbit, let alone one early enough to give it a fighting chance of success. We just didn’t have the evidence to support making such a decision, and there was no realistic way in which we could have had that evidence by the time that decision needed to be made.

The CAIB asked us about the scenario in early May 2003. Admiral Gehman, a superior leader, intentionally waited to ask the question until some of the raw emotions had time to subside a little.

When we saw the analyses, there was no grumbling, but there was grief. We couldn’t save the ship. Columbia was doomed, no matter what. Maybe we could have saved the crew. But there were so many what-ifs and assumptions, so many things that had to go completely differently from the very first hours of the mission. Would it have been successful? I don’t know. But we never even had the chance to try.

As much as it hurt people to think about the remote possibility of saving Columbia’s crew, the study helped prompt discussions on how to save a future crew of a damaged shuttle. The studies led to the safe-haven scenario, in which damaged Orbiters could dock at the International Space Station to enable the crews to wait there for a later rescue mission.

KSC and JSC used the Columbia rescue scenario to design a one-time rescue mission that could back up the final Hubble servicing mission. After the successful completion of STS-121 in July 2006, proving that we’d finally solved the foam-shedding problem, NASA Administrator Mike Griffin formally approved the Hubble servicing mission.

On May 11, 2009 Atlantis was poised for launch to the Hubble from Pad 39A at Kennedy. Standing on Pad 39B two miles to the north was Endeavour, ready to go into orbit if there were any problems with Atlantis. For the first and only time, NASA had two shuttles in launch countdown simultaneously. We were ready to launch Endeavour one day after Atlantis if necessary. Tremendous dedication and work went into getting us to this dual launch posture. Fortunately—like many other things in the space business—this contingency capability was assured but never needed.

Atlantis’s flight went flawlessly, so the rescue mission never flew. Atlantis’ crew successfully prolonged Hubble’s life and upgraded its instrument package.

In a roundabout way, Columbia had once again contributed to the advancement of scientific discovery.

STS-125 and sts-400
On Pad A (foreground), Atlantis awaits launch for the STS-125 Hubble servicing mission, while Endeavour (STS-400) sits on Pad B for a possible rescue mission. (NASA/Troy Cryder)

The Day We Launched Early

This posting doesn’t relate to the Columbia accident, but it addresses a question I get on my monthly KSC tours offered through the Kennedy Space Center Visitor’s Center.

Why were the launch windows for flights to the International Space Station 10 minutes long, while others—especially early in the program—were 2.5 hours long? The answer is Rendezvous.

Without getting into a mini-course on orbital mechanics, for ISS missions we had to get to a specific point in orbit while the station was there. That’s pretty clear. The trick is that the Shuttle had to do it with the available fuels on board—those in the Solid Rocket Boosters, the Shuttle Main Engines, and the Orbital Maneuvering System and thrusters. Simplistically, that total is called the ‘performance’ of the entire system. The launch window was in large part defined by it. It said we had to launch at a time that when after the Shuttle reached orbit it was close enough to ‘catch’ the ISS with the least amount of maneuvering fuels necessary. If too far away, more fuel would have been needed than was available. Rendezvous would have been impossible. Mission failure. So that permissible distance in orbit defined exactly when launch had to occur. And the least fuel would be used if we launched at that precise time, called the ‘preferred time’. The available maneuvering distance once in orbit said rendezvous could still happen if we launched about 5 minutes before or 5 minutes after the preferred time, again, all based on fuel usage. Thus the 10 minute launch window.

In contrast, for missions not requiring rendezvous, like deploying a satellite or STS-107’s Spacehab mission, just getting to the proper orbit was the main objective. It didn’t matter quite as much when—just that the Shuttle got there. The length of the window was defined by other parameters. Usually the most constraining one was the length of time the astronauts could spend on their backs strapped in the Orbiter awaiting launch. This was 5 hours 15 minutes. Given the time the first astronaut (the Commander) got into the shuttle before launch was usually 2 hours 45 minutes before the scheduled T-0, it resulted in a 2.5 hour launch window. There you go!

But what about ‘launching early’? How can that be?

Flash back to August 10, 2001, Discovery’s launch day for STS-105. The mission was to take the Leonardo Multi Purpose Logistics Module (MPLM) to the International Space Station. Our launch attempt on the previous day was scrubbed due to weather. Today, all was going well in the Firing Room for launch, but a mid-summer storm was pounding Lake Okeechobee, approximately 110 miles south of the launch pad, and the storm was moving north. Heavy rain and lightning were heading at us with no expectation to dissipate. Time of arrival in our area was calculated to be about T-0. Weather launch commit criteria were going to be violated—no way around it. If we scrubbed today, we would have a several-day turnaround before the next launch attempt, as we would have to top off the cryogenics aboard the Shuttle. The only hope was to launch as soon as possible and beat the storm’s arrival.

By rule and practice, how the available launch window was used was at the Launch Director’s discretion (within reason of course!). I called the Flight Director in Houston and discussed my idea to launch at the beginning of the 10-minute window rather than in the middle as we had planned. He liked the idea, so we accelerated countdown beginning about 2 hours prior to liftoff, to save the 5 minutes.

All worked out well. We launched at the opening of the window, 5 minutes early, about 20 minutes before the lightning sensors went out of limits. We beat the storm!

Launching early worked. It was never done before or after. STS-105 holds the distinction as the only manned mission ever to ‘launch early’.

STS-105 launch ksc-01pp-1467
Whew! Discovery beats the storm, as STS-105 becomes the only manned mission to launch ahead of the announced launch time. (NASA photo)

What to Do with the Debris?

Fourteen years ago, in early April 2003, we were about 2/3 of the way through recovering Columbia’s debris from Texas, although we didn’t know it at the time. But the number of debris trucks arriving at the reconstruction hangar at Kennedy Space Center had begun to tail off in the preceding weeks, so we knew at some point they’d stop altogether.

Two initiatives were being worked at that time. First, what to do with the debris, and secondly, how would debris found after operations ended in Texas find its way to us? What were the people finding items after the recovery operations ended to do with the material they found?

I’ll briefly address both now, with the intent to more fully discuss them in subsequent postings.

As stated in a previous entry in this blog, Administrator O’Keefe was instrumental in the decision to learn from Columbia’s accident and in particular, from the debris. Having gotten his unofficial “go” to develop the concept to study the debris, the task to actually put the concept into practice fell on a few of us in the hangar. I asked Scott Thurston, Columbia’s NASA Vehicle Manager, to develop the necessary plans. He did an outstanding job. He and a very small group debated where to store the debris, how to “advertise” that it even existed for study, the requirements for organizations to obtain select pieces, the logistics of lending it to them (it’s not easy lending government property to private organizations), and the proper approval authorities and documents. And, by the way, how to do this for many years to come – also not easy.

The results of their labor and Scott’s leadership are clear. The debris loan program is very much still alive, with several hundred pieces either actively out for study or with studies already concluded. The material is stored in a climate-controlled room in the Vehicle Assembly Building, also allowing easy access for employees to view it. It has a full-time NASA curator—Mike Ciannilli—who also developed and runs NASA’s Apollo, Challenger, Columbia Lessons Learned Program. Mike was very active in the debris recovery as an aerial searcher in Texas, and his passion for sharing the lessons makes him the perfect person for the job.

As with debris from Challenger, some pieces of Columbia continue to be found. To deal with this in Texas, a program involving local authorities is charged with taking calls from anyone finding pieces that may be from Columbia. They in turn call Ciannilli, who is responsible for determining the authenticity of the find and returning the material to KSC to join the other 84,000+ pieces of the ship’s debris.

The most “famous” piece found in this manner was a cryogenic tank from Columbia‘s fuel cell system that had been submerged in Lake Nacogdoches since February, 2003. A severe drought in the summer of 2011 lowered the lake level to the point that the tank was high and dry.

tank lake nacogdoches
An aluminum cryogenic tank from Columbia’s fuel cell system, uncovered in Lake Nacogdoches in August 2011, more than eight years after the accident. (NASA photo)

Numerous other pieces have been found by farmers, ranchers, hikers, etc. I suspect debris will continue to be found from time to time. We know for certain that three of the six main engine turbine pumps are still out there somewhere. But like the three that we recovered, they are no doubt buried deep in the East Texas or Louisiana dirt or at the bottom of a body of water. They will probably never be found.

powerhead
One of Columbia’s powerheads—found buried fourteen feet under the Louisiana mud. (NASA photo)

We officially wrapped up recovery operations in early May, 2003. The vast majority of Columbia that we will ever find is already home. And some of it is being used to advance our understanding in materials and structures subjected to extreme conditions. The goal is to design future spacecraft that can better withstand such conditions. One such example is a seat design capable of withstanding very high torsional forces.

Columbia continues her scientific and research missions, well after her last space flight. That legacy would have made her final crew proud.

The Recovery Passes the Halfway Mark

At the beginning of April 2003, the search efforts for recovery of Columbia‘s debris passed the halfway mark.

From the time operations went into full swing at the end of the third week of February, the Texas Forest Service had overseen the mobilization of more than 12,200 men and women from the National Wildfire Coordinating Group. These firefighters came from more than forty states and Puerto Rico.

April 1 ground search status
Firefighters came from nearly every US state and Puerto Rico to search for Columbia’s wreckage. This map shows the number of wild land firefighters and support staff deployed by each state as of April 1, 2003. 

They entered the recovery zone through a processing facility set up by the Texas Forest Service in Longview, Texas. After an orientation on what they were looking for and the hazards they might encounter, the fire crews and their supervisory Incident Management Teams were deployed to camps in Corsicana, Palestine, Nacogdoches, and Hemphill. These towns were spaced roughly fifty miles apart along the debris field. The crews then spent two to three weeks conducting grid searches in their assigned areas. Then they were rotated out and replaced by fresh crews.

Longview cots
Cots for transiting fire crews in the Longview staging camp. (Photo by Jan Amen)

Their efforts produced astonishing results. As of April 2, 2003, the crews had searched every foot of an area of 426,844 acres (667 square miles). They had recovered 65,730 pounds of material from Columbia, equal to about 29% of the vehicle’s weight. Their efforts were also being supplemented by 37 helicopters, 8 fixed-wing aircraft, and salvage divers and surface boats in Lake Nacogdoches and the Toledo Bend Reservoir.

In this first incident response by the newly-created Department of Homeland Security, FEMA coordinated the federal agencies and funded the operations. NASA managed the overall search and provided technical assistance. The Environmental Protection Agency identified and handled hazardous materials, and transported all materials recovered during the search. The Texas Forest Service coordinated the air and ground searches. The US Forest Service, the Bureau of Land Management, the Bureau of Indian Affairs, and the National Park Service provided the majority of the search crews and equipment. The US Navy and Coast Guard conducted the water searches.

Those are just some of the lead agencies. More than ninety federal, state, and local government agencies assisted in some way with the aftermath of the Columbia accident.

It was on the surface a collaboration of unlikely partners, but each agency brought its core expertise to bear in the largest and most remarkable inter-agency operation ever conducted.

Astronaut Jerry Ross told me during an interview for the book that “people first and foremost need to understand the greatness of the United States and its citizens. The United Sates has an incredible wealth of capabilities. To see the energy and expertise and materials and technical capabilities that descended on Lufkin within hours of the accident was so reassuring.”

In times when we hear people complaining about “government incompetence,” it’s helpful to remember that agencies are made up of people. People—not faceless agencies—get the work done. And we need to know that our federal and state agencies are made up of a lot of motivated and dedicated people who want to see our country be successful.